Current Project Status

On December 13th, members of the Building Committee presented the proposed Site Plans to Uwchlan Township for informational purposes. This was mainly to introduce our project to the township and answer any of their questions. The meeting went well, and we achieved our goal of getting feedback before formally applying for a development permit.

We also developed General Contractor Prequalification Forms which we have given out to potential contractors. This will help us gather information to make an informed decision as to which contractors to hire for our project.

And finally, we are preparing the preliminary land development and erosion control plans that are required.

What’s Ahead in January

  • Request prequalification forms from general contractors
  • Continue to develop Civil Engineering documents to submit to the township in the coming months
  • Review Utility Metering (water, sewer)